In July 2013, SALCO signed the Turkey’s TOSYALI altitude project cargo transportation EPC contract with its customer and was responsible to organize all the cargo’s transportation. After nearly 1 month’s preparation, the first cargo gathered at the port around August 10th ,loaded on August 22nd ,and forwarded to ISKENDURUN PORT from SHANGHAI PORT by vessel MV.HARRISON M. Most of the first cargo was heating furnace of steel structure and 8 large bridge crane, adding uo to 4500FT(including 16 pieces of 30m-long crane crossbeam). SALCO’s employees worked in the front line deligently for over half a month from receiving cargo to colligation. The 16 pieces of 30m-long crane crossbeam was the biggest in amount. During the operation, SALCO’s employees picked a lot of urltra large cargo transportation experience.