Authorized by our customer, SALCO took part in the development of early stage shipment plan for the construction project of power station TUBASTE in South Africa from May 2012,meanwhile, SALCO also got well prepared to operate .In September 2012, SALL’s TUBASTE project formally initiated when the first batch of container cargo—ACCTB(Air Cooled Condenser Tube Bundles)—all about 23*40GP in total started shipment. The length of single piece of ACCTB was almost 10m,and both the height and width were 2.2m,weighted 15.3t. In order to cut down the cost ,SALCO negotiated with the manufacturer for many times and finally reached an agreement to replace the OT containers with the GP containers which could simplify the unloading process in the program’s field. SALCO’s effort was highly appreciated by the customer.